Installation debugging and use maintenance for CIP system

HOME > FAQ
installation and debugging for CIPCIP cleaning system circulates specified cleaning solutions through processing equipment to clean its internal food-contact surfaces.
There are acid tank, alkali tank and water tank manufactured by  stainless steel, which set with an insulation layer. Feed pump entrance is connected with the bottom of three tanks and controlled by the electromagnetic valve. The outlet is connected with the upper entrance of three tanks and controlled by the electromagnetic valve. A sewage outlet is arranged on the lower part of each storage tank and the tank is provided with a thermometer and a liquid level display device. There is a section used for preparation of cleaning agent in the top of tank. The tank is also provided with a vent pipe to discharge exhaust gas.

Installation and debugging  

  1. Position acid, alkali and water tanks according to the supplied equipment layout and site requirements. Correct the perpendicularity of per tank and the level of centrifugal pump. Distributor needs foundation bolt to be reinforced.
  2. Route CIP discharge to the plant's approved collection or treatment system; confirm chemical compatibility and local discharge requirements before connecting drains.
  3. Have qualified installers connect the pump, water and, where specified, steam and condensate lines using the supplied piping diagram and pressure ratings.
  4. Install every tank’s thermometer, liquid level meter and all kinds of instruments components. When installation, according to the implementation of the instructions for the use of the product.
  5. The installation of electrical equipment and control devices need to be carried out by professionals, which should be strictly in accordance with the relevant provisions of the operation. Confirm protective grounding and test controls and interlocks during commissioning.
  6. After the installation of all kinds of pipeline, water leakage test should be done to ensure no leakage.

Use maintenance

use maintenance for CIP system
Use

  • Clean the equipment before use.
  • Starting power supply.
  • Prepare cleaning solution and verify its concentration in the acid tank and lye tank. Fill each tank to the operating level specified for the installed system; do not apply a universal 80% fill rule.
  • Correct the accuracy of the instrument. According to the process requirements, adjust the control point value.
  • According to the requirements of the cleansing process, set continuous cleaning time of acid, alkali and water.
  • Connect the distributor to the equipment to be cleaned or pipeline system to be cleaned.

Maintenance

  • If a pump, valve or pipe connection leaks, stop the affected cycle, isolate pressure, heat, chemicals and hazardous energy as required, then have trained personnel repair or replace the affected part. Regular maintenance equipment, keep clean and implement the regular maintenance system, so that the equipment is always in a good and reliable working state.
  • Monitor cleaning-solution concentration using the approved method. Trained personnel should adjust chemicals under the site procedure and the chemical supplier's instructions.
  • Equipment lubrication: motor should be maintained regularly in accordance with the lubrication requirements of the motor manufacturing plant.
  • Instrument, electrical components, motor and purchased parts according to product instructions for maintenance.
  • When taking the system out of service, handle remaining acid and alkali separately under the site chemical-handling and disposal procedure, then clean and inspect the equipment.
  • Replace or reuse cleaning solution according to a validated site procedure that checks concentration, soil load and cleaning effectiveness. Do not assume that one-use or repeated-use rules apply to every system.